Works in Bulebel substation in connection with the installation of Photovoltaic (PV) Panels.

28.02.2023

The installation of photovoltaic systems, especially for large installations, entails major works in substation prior allowing the produced electricity be fed into the national grid.

Our engineers and technicians have just completed works to replace cables and substation equipment in Bulebel that will be receiving the energy supplied from a PV system implemented on one of the factories within the industrial estate.

This PV installation will generate 272kW which will be fed into Enemalta grid.

This is another clean and sustainable energy project.